Question 1 of 25
1. Question
?In which knowledge area is it determined what activities are needed in order to complete a business analysis effort
Correct
Incorrect
Unattempted
Question 2 of 25
2. Question
.Your organization is using a plan-driven approach to business analysis
?What must you do with all of the communication documents created as part of this high-priority project that you are serving as the business analyst for
Correct
Incorrect
Unattempted
Question 3 of 25
3. Question
?What plan includes the description of the scope of work, the deliverable Work Breakdown Structure, the activity list, and estimates for the business analysis activities
Correct
Incorrect
Unattempted
Question 4 of 25
4. Question
You are the business analyst for your organization. You are coaching Tom about the different approaches to business analysis. Which type of business analysis approach has the most business analysis work at the beginning of the project or during the start of a project phase?
Correct
Incorrect
Unattempted
Question 5 of 25
5. Question
?Which of the following process models needs to complete each set of tasks in one phase before moving into the next phase in a project development life cycle
Correct
Incorrect
Unattempted
Question 6 of 25
6. Question
?You are the business analyst for a solution that has 435 stakeholders. How many communication channels exist in this project
Correct
Incorrect
Unattempted
Question 7 of 25
7. Question
?Which statement about business analysis stakeholders is false
Correct
Incorrect
Unattempted
Question 8 of 25
8. Question
?As the board members of a company change, which plan should the business analyst update first
Correct
Incorrect
Unattempted
Question 9 of 25
9. Question
?Identifying key stakeholder roles and selecting requirements activities is done as part of which knowledge area
Correct
Incorrect
Unattempted
Question 10 of 25
10. Question
?What defines the business analysis team roles, deliverables to be produced, and tasks to be performed
Correct
Incorrect
Unattempted
Question 11 of 25
11. Question
Which of the following activities would Maria (BA) most likely not include in her governance document?
Correct
Incorrect
Unattempted
Question 12 of 25
12. Question
?A business analyst realizes that from now on, the CEO is no longer going to sign off the QA instructions. Which document should she propose to update in priority
Correct
Incorrect
Unattempted
Question 13 of 25
13. Question
.A business analyst (BA) is capturing the requirements for an application which displays information on a mobile device
.The information will be extracted from a database owned by another department within the organization
?Which of the following will identify the stakeholder who can approve access to the database
Correct
Incorrect
Unattempted
Question 14 of 25
14. Question
?Requirements management policies are included in which plan
Correct
Incorrect
Unattempted
Question 15 of 25
15. Question
.A business analyst (BA) elicits requirements for the sales order processing of multiple product lines
.Elicitation reveals that the business processes for the sales orders of most products follow similar activity patterns that have been established over a number of years
.Some of the new proposed seasonal products, however, will necessitate major variations in the process flow of some departments
.The seasonal products are likely to be different every year
The business needs to carefully adapt its business practices so that the significant but seasonal variations in some of the business processes
.for the new products are handled adequately without disrupting the processes for the other established products
?Which of the following approaches must the BA take to manage the requirements for sales order processing in the long term
Correct
Incorrect
Unattempted
Question 16 of 25
16. Question
?After entering an organization, the business analyst realizes that this organization did not have a plan to reuse its requirements. What is the first step of a business analyst
Correct
Incorrect
Unattempted
Question 17 of 25
17. Question
.You are the business analyst for your organization
.Management has asked you to define and document the requirements of an endeavor so that the requirements may be reused again in the organization
?Why would an organization want to re-use requirements
Correct
Incorrect
Unattempted
Question 18 of 25
18. Question
?Which Requirements Attributes is mandatory for any RTM
Correct
Incorrect
Unattempted
Question 19 of 25
19. Question
?There are four inputs to the plan business analysis activities. Which one of the following is not an input to the plan business analysis activities process
Correct
Incorrect
Unattempted
Question 20 of 25
20. Question
?What key input is used to plan the business analysis approach for a project
Correct
Incorrect
Unattempted
Question 21 of 25
21. Question
.You are a business analyst working on a project where the timing of the business analysis work is early in the project life cycle
?What type of business analysis approach best fits this project
Correct
Incorrect
Unattempted
Question 22 of 25
22. Question
?Which deliverable defines how requirements will be managed for reuse in an organization
Correct
Incorrect
Unattempted
Question 23 of 25
23. Question
?You are currently planning the business analysis information management approach for your project. What activities will you be performing as part of this task
Correct
Incorrect
Unattempted
Question 24 of 25
24. Question
.You are the business analyst for your organization. On your current project you’ll be using the change-driven approach for defining requirements and gathering feedback
?Which of the following statements best describes the change-driven app
Correct
Incorrect
Unattempted
Question 25 of 25
25. Question
.A business analyst (BA) is reviewing the performance results from a recent change initiative
.One of the results stated, “The planned schedule expected 50% of the project to be done at milestone 6
.The schedule performance index (SPI) was 87%
?Three project team members worked overtime to ensure that the actual schedule would align with the planned schedule.” This is an example of what type of action
Correct
Incorrect
Unattempted